Significant progress has occurred over the past couple of months, and we’re excited to share these updates with you.
Friendship Store
Friendship Store is taking shape! We are now five months into what we estimate to be a 12-month construction schedule. After a delay earlier in the winter due to utility relocations, we have seen considerable headway in the past few weeks. The two-story frame of the building is beginning to take shape (see pic above). The steel structure of the building should be completed this week. READ MORE
Welcome, Raynardo Williams
Seward Co-op has hired Raynardo Williams as the store manager of the new Friendship Store. As a former entrepreneur, Raynardo is accustomed to the work required to bring a vision like the Friendship Store to fruition.
“I’m used to being very hands on,” he says. “I like getting my hands dirty on projects.” READ MORE
Co-op Creamery
Work on the Co-op Creamery at 2601 E. Franklin Ave. continues. In late January 2015, co-op administrative staff moved into the Creamery Building’s second floor offices from the Franklin store. This move has helped to alleviate space constraints at the Franklin store offices. The staff at the Creamery will support all Seward locations. READ MORE
Welcome, Chad Snelson
Creamery Cafe Production Manager: Seward Co-op has hired Chad Snelson as director of operations at Seward Co-op’s Creamery Kitchen and Co-op Creamery Neighborhood Café. At this point, with the café still under construction, it’s been a lot of planning and forecasting for Chad.
“Planning is fun,” says Chad, “but actually doing it is way more fun.” READ MORE